Help us finish our Nature Trail & Bridge project before our ribbon cutting celebration

Good news, we see the finish line on this project. The bridge is done, we just have some rock walls to finish and crushed rock to spread. With large volunteer turnouts both Friday and Saturday we’ll finish it just in time for the ribbon cutting celebration on September 28th. We are starting at 9:00AM bothContinue reading “Help us finish our Nature Trail & Bridge project before our ribbon cutting celebration”

Join our work party this Friday and Saturday, Aug 24/25

We need your help this weekend. It is going to be nip and tuck to meet our schedule. While the bridge is assembled we will need to have a good turnout on Friday and Saturday to stay on schedule for the September 28th ribbon cutting ceremony with the Mayor. This year we’ve been averaging sixteenContinue reading “Join our work party this Friday and Saturday, Aug 24/25”

Major bridge progress on July 27/28

We got a lot done on the bridge on Friday the 27th and Saturday the 28th. Here’s Art Tuftee applying the torchdown on top of the glulams. Jerry Granahan drills a hole through the glulam. With the glulams in place and attached to the concrete footings we were ready to begin attaching the railings onContinue reading “Major bridge progress on July 27/28”

The glulams for the bridge are in place

Art Tuftee has been our project lead on our Nature Trail and Bridge project. This past Friday and Saturday we moved two 36′ glulams a quarter of a mile into the bridge site. Moving the glulams one at a time, two Dingos carried each end until they got to a sharp turn in the trail.Continue reading “The glulams for the bridge are in place”

Join us for bridge building this Friday and Saturday

We mixed, transported and poured the concrete last weekend and it went exactly as planned. We moved the 36′ White Alaskan Cedar Glue Lams close to the bridge site. This weekend we’ll strip the forms and set and affix the beams. We hope you’ll want to be a part of this important milestone. On FridayContinue reading “Join us for bridge building this Friday and Saturday”

Friday and Saturday were great sessions

We had a great group of volunteers join us on Friday and Saturday this week to get the concrete bridge footings poured. On Friday the two 36′ glulams were delivered. They were carefully moved down the trail closer to the bridge site. On Saturday Art Tuftee setup a high line across the creek where theContinue reading “Friday and Saturday were great sessions”

Help us pour concrete bridge footings this Friday

Our bridge is still on schedule and we hope to keep it that way. Our plan is to mix, transport, and pour concrete Friday and Saturday. We will also be moving 36′ White Alaskan Cedar Glue Lams in to the bridge site. Unfortunately this week we do not have a session sponsor, so we hopeContinue reading “Help us pour concrete bridge footings this Friday”